To view the global workload of multi-project resources, go to the “All” tab.
Go to the Gantt tab, then activate the load switch.
The figures that appear represent the remaining capacity in hours for a given day (if your Gantt is set to day mode).
Remaining capacity is calculated as follows :
For a given day : Daily capacity - workload : Remaining capacity
To modify the workload, you can edit from the Gantt the number of hours allocated to resources for their tasks.